Construction works in the second building of the MONAcomplex are in full swing. Concrete slab has been poured at K= +9,00 m. Backfill around the building and in the West and South sections has been completed, waterproofing on the basement walls on the north side is being executed, as well as masonry at K=-6,80 m and elevation 3,00 m. Formwork of slab K=+12,00 m is executed. The staircase of the vertical layout is also concreted.
You are also welcome to visit our newly opened Sales office in the MONA 1 building. Due to the strong interest in the sq. Manastirski livadi - East and MONA complex, on site, every weekday from 10:30 to 19:30 Sales Manager - Lidiya Mladenova, can tell you about the project and new developments around the quarter. Mládina will give you information about the project.