Construction stage - Complex MONA - first building 20.07.2018

Construction stage - Complex MONA - first building 20.07.2018

Stage of construction - MONA

Less than a month ago, the MONA project was doing the verticals from elevation -6.46 to elevation -2.96. In the last week, we already have a half-concreted slab at the -2.96 level, and the rest is due to be completed next week.

A second crane has already been installed on site and the water table is being maintained at almost zero.

The waterproofing on the east side is expected to start next week.


Take a look atthe available apartments in the MONA complex, and for more information fill in the enquiry form - one of our consultants will contact you immediately.