Stage of construction - MONA
Less than a month ago, the MONA project was doing the verticals from elevation -6.46 to elevation -2.96. In the last week, we already have a half-concreted slab at the -2.96 level, and the rest is due to be completed next week.
A second crane has already been installed on site and the water table is being maintained at almost zero.
The waterproofing on the east side is expected to start next week.